How Much Concrete Do I Need? Slabs, Footings and Post Holes
Working out how much concrete you need is length times width times depth, with every dimension in the same unit, plus an allowance for waste. The math is easy. The mistakes come from mixing inches and feet, measuring a perfect rectangle when the ground is not flat, and ordering exactly the calculated amount with nothing spare. This page walks through slabs, footings and post holes with worked numbers, then converts the result to cubic yards, cubic meters and bags.
The basic formula
Volume (cu ft) = length (ft) x width (ft) x thickness (ft)
Thickness is usually given in inches, so divide it by 12 first: 4 in is 0.333 ft, 6 in is 0.5 ft, 8 in is 0.667 ft. Then:
- Cubic yards = cubic feet / 27. Ready-mix is sold by the cubic yard in the US.
- Cubic meters = cubic feet x 0.0283. One cubic yard is about 0.76 m3.
- Bags = cubic feet / yield per bag. An 80 lb bag of premixed concrete yields about 0.60 cu ft, a 60 lb bag about 0.45 cu ft and a 40 lb bag about 0.30 cu ft.
Slabs, patios and paths
Example: a 10 x 10 ft patio, 4 in thick.
- 10 x 10 x 0.333 = 33.3 cu ft
- 33.3 / 27 = 1.23 cu yd (0.94 m3)
- Add 10% for ordering ready-mix: about 1.36 cu yd
- In 80 lb bags: 33.3 / 0.60 = 55.6, plus 5% = 59 bags. In 60 lb bags, 78. In 40 lb bags, 117.
For an L-shaped or irregular slab, split it into rectangles, work out each one and add them. For a circle, area is 3.14 x radius x radius (radius in feet), then multiply by thickness.
Common thicknesses for context: walkways and patios are often 4 in (100 mm); driveways commonly 4 to 6 in (100 to 150 mm) depending on soil and vehicles. Anything carrying a building or vehicles is structural: check your plans and local code, which set the thickness, base and reinforcement.
Footings
A continuous footing is a long, narrow slab. Example: 40 ft of footing, 16 in wide and 8 in deep.
- 40 x 1.333 x 0.667 = 35.6 cu ft
- 35.6 / 27 = 1.32 cu yd (1.01 m3), or about 1.45 cu yd with 10% added
Footing width and depth are not something to pick from an example. They come from the plans, a structural engineer and the local building code, which depend on the load, the soil and the frost depth, and footings usually need a permit and an inspection before the pour. Measure the trench as dug, not as drawn: trenches are rarely exactly the design width, and the extra width fills with concrete.
Post holes and round columns
Volume of a cylinder = 3.14 x radius x radius x depth, with radius in feet (diameter in inches / 24).
Example: a fence post hole 10 in across and 3 ft deep, holding a 4x4 post (actual size 3.5 x 3.5 in).
- Hole: 3.14 x 0.417 x 0.417 x 3 = 1.64 cu ft
- Post displaces 3.5 x 3.5 / 144 x 3 = 0.26 cu ft
- Concrete: about 1.38 cu ft per hole, or 3 bags of 80 lb (4 of 60 lb) with 5% waste added
Holes dug by hand tend to bell out at the bottom, so real use is often higher. For a run of posts, multiply by the number of holes and round up the bag count for the total, not per hole. The same formula covers round column forms such as cardboard tubes, which are structural if they hold up a deck or a roof: their diameter, depth and reinforcement come from the plans or code.
Steps
For a set of solid steps, work out each step as a block from the ground up: the bottom step is the full depth of the whole flight, the next is one tread shorter, and so on. Add the blocks together. If the steps are poured over compacted fill, subtract the fill.
Why add extra, and how much
Concrete runs out at the worst possible moment: halfway along the last form, with the surface starting to set. Extra covers:
- uneven subgrade (a base that is 1/2 in low across a 4 in slab means about 12% more concrete in that area)
- forms that bow outward under the weight of wet concrete
- spillage, what stays in the mixer and barrows, and what the truck chute holds back
Our concrete volume calculator adds 10% to the cubic yard figure for ordering ready-mix, and the concrete bag calculator adds 5% and rounds up to whole bags. If the ground is rough or the slab thickens at the edges, allow more. A thickened edge on a slab is a small footing in its own right: add it as a separate strip.
How to measure the job
- Measure length and width inside the forms, not the outside of the boards.
- Measure depth in several places, from the top of the form to the compacted base. On a large slab, run a string line across the forms and measure down at a grid of points, then use the average.
- Write every measurement in the same unit before multiplying. Mixing inches and feet is the most common estimating error, and it is usually off by a factor of 12.
- Round up, never down, when you order.
Bags or a truck?
One cubic yard is 27 cu ft, which is 45 bags of 80 lb concrete before waste (48 with 5% added), or roughly 3,600 lb of bags to lift, open and mix. Many people find that past about a cubic yard, a ready-mix truck or a mixer trailer is the easier and more consistent option, especially for a slab that must be finished in one go. See ready-mix truck or bagged concrete for how to decide.
If you are mixing your own from cement, sand and gravel
Cement, sand and gravel shrink in volume when mixed with water, because sand fills the gaps between stones and cement fills the gaps in the sand. So the dry materials take up more room than the finished concrete. A common rule is to multiply the wet volume by about 1.54 to get the total dry volume, then split it by the mix ratio. Our mix ratio calculator does this and counts cement in 50 kg bags of about 1.25 cu ft.
Safety when you handle the material
Whatever the quantity, wet concrete burns skin: it is strongly alkaline and the burns may not hurt until hours later. Wear alkali-resistant gloves, long sleeves and trousers, waterproof boots with trousers over the tops, and eye protection, and wash any splashes off with clean water promptly. If it gets in your eyes, rinse with clean water for at least 15 minutes and get medical help. Open dry bags upwind with a dust mask on. An 80 lb bag is a heavy lift: lift with your legs, get help, and move bags with a barrow.